Project Scope
The project footprint covers a 5,600 foot stretch of SW 257th Drive and its right-of-way frontage on both the east and west sides of the road. The project limits contain all intersections between SW Cherry Park Road (north end of the project) and SE Stark Street (south end of the project). Ramp and curb improvements will occur at all affected intersections while two enhanced crossings will be placed near the 2,100 and 4,800 foot marks (measured from north end of project).
Roles & Responsibility
- Conflict Matrix and Conflict Maps
- Communicating with utility providers to identify potential conflict mitigation
- Oversight and tracking of project deliverables – including Utility Manage Utility Conflict Notification letters